Environmental & Social Safeguards

  • Policy Document on Environmental Safeguards
  • Policy Document on Social Safeguards
  • Environmental & Social Reports

Grievance Redress Mechanism (GRM)

  • A 3-tier GRM system has been adopted under HELP.
  • The PIU and national-level Grievance Redress Committees (GRCs) have been started.
  • Local (upazila) level GRCs are being formed.
  • Notifications have been issued to Upazila Engineers, and committees are being established.

GRC Formation Status

Community-level GRCs have been completed in 11 of the 17 upazilas across the 2 districts. At camp level, 1 GRC has been formed, in Ukhiya, out of the 3 upazilas concerned (Teknaf, Ukhiya and Hatiya).

DistrictUpazilaCommunity LevelCamp Level
Noakhali Noakhali Sadar Done Not required
Noakhali Companyganj Done Not required
Noakhali Begumganj Not formed yet Not required
Noakhali Hatiya Not formed yet Not formed yet
Noakhali Subarnachar Done Not required
Noakhali Kabirhat Not formed yet Not required
Noakhali Senbagh Done Not required
Noakhali Chatkhil Not formed yet Not required
Noakhali Sonaimuri Done Not required
Cox's Bazar Teknaf Done Not formed yet
Cox's Bazar Ukhiya Done Done
Cox's Bazar Cox's Bazar Sadar Not formed yet Not required
Cox's Bazar Ramu Done Not required
Cox's Bazar Chakaria Done Not required
Cox's Bazar Moheshkhali Not formed yet Not required
Cox's Bazar Pekua Done Not required
Cox's Bazar Kutubdia Done Not required

Safeguards Screening Status

ESSR: Environmental and Social Screening Report.

4 nosSurvey and Screening Completed
3 nosESSR Submitted to the World BankHELP-CEMCRP-1/A, HELP-FSCD/BD-1 and HELP-COX/BR-1
2 nosESSR Cleared by the World BankHELP-CEMCRP-1/A and HELP-FSCD/BD-1
1 noESSR under Preparation at the PIUHELP-COX/CS-1

Focus Group Discussions (FGD)

Focus Group Discussions on environmental & social issues