Landing Stages
Landing Stages and Jetties for River and Sea Access
Target of the Project
6 nosConstruction of Landing Stage
Packages
| Package No. | District | Description | Quantity | Method & Type | Cost (Lakh BDT) | Status |
|---|---|---|---|---|---|---|
| HELP-CEMCRP-1/B | Cox's Bazar | Construction of Carry Forward EMCRP Incomplete Grokghata Jetty at Moheshkhali under Cox's Bazar District. | 1 no | OTM (National) | 4,032.59 | Tender document preparation is ongoing |
| HELP-NOA/LS-1 | Noakhali | Construction of 2 nos. Landing Stage (Chairman Ghat & Nalchira Ghat) under Hatia Upazila | 2 nos. | OTM (National) | 8,128.00 | — |
| HELP-NOA/LS-2 | Noakhali | Construction of 4 nos. Landing Stage (Nijumdwip, Muktaria, Tomuruddin Ghat & Aska Bazar Ghat )under Hatia Upazila | 4 nos. | OTM (National) | 5,000.00 | Estimate preparation is in progress |
| Total | 17,160.59 | |||||